|
Sediment
Problems at Three Gorges Dam
Professor
Luna
B.
Leopold
University
of
California
,
Berkeley
The Three Gorges Dam is designed to operate under conditions practically
untested in the world and never before tested in such a large structure.
Projections of controlling sedimentation within the reservoir are subject
to significant uncertainties.
China
has about 83,000 reservoirs built for various purposes, of which 330 are
major in size. Sediment deposition in 230 of them has become a significant
problem, resulting in a combined loss of 14 percent of the total storage
capacity. In some, more than 50 percent of the storage capacity has been
lost.(1)
The proposed operating procedure at Three Gorges is as follows: during the
flood season (May through September), the reservoir level would be held at
a low pool elevation, called the Flood Control Level (FCL). During this
period inflows are used for power generation. After the flood season, the
lower flows with lower sediment concentration will be impounded, and the
reservoir pool level will rise to the Normal Pool Level (NPL).
It is proposed that in time, sediment will be deposited in the reservoir
until a uniform slope of the bed will be established that can just
transport the annual sediment load through the reservoir. It is estimated
that this condition will be reached between 70 and 150 years after
construction, depending on the choice of the elevation for the Flood
Control Level (FCL).
There are an estimated seventeen reservoirs in the world that operate in
this manner, seven of which are in
China
and one in the
United States
.(2) All of these except one are small in size. That exception is
Sanmenxia in
China
, which has only eighteen percent the storage capacity of Three Gorges -
in other words, very much smaller. Thus the world's experience with this
type of operation is very meager.
These uncertainties lead to the conclusion that significant fiscal
forecasts that presume to support the financial benefits expected may be
in error and that investing in the project would be unwise. There are
several sources of such error in dredging costs, resettlement costs, flood
control benefits, and other areas, but the present discussion deals with
the problems only in the subject of sedimentation.
The sedimentation conditions at various times during the first 100 years
of operation have been forecast by use of mathematical models and physical
analogues that involve many assumptions of unverified reliability. Any
difference between the forecast and on-the-ground performance has large
financial, environmental, and humanistic implications. Therefore, it is
necessary to specify some of the most important possible sources of error
in the forecasts.
The largest dam construction projects in the United States - Hoover, Glen
Canyon, Bonneville, Ft. Peck, Tennessee Valley, to name a few - do not
utilize the principal of sediment flushing or sluicing contemplated for
Three Gorges, but some of the same uncertainties were present in their
design. The American experience gives some direct insight into possible
future uncertainties. Perhaps the most important lesson gleaned from
direct experience is that conditions 50 years in the future are usually
quite different from any forecast, and 100 years in the future are simply
not forecastable.
One problem is in the ability of designers to forecast the rate of
sediment accumulation in a reservoir. Even when the records of sediment
inflow are reliable, the deposit rate is often quite unanticipated. For
the multi-purpose reservoirs in
India
, Murty states that the "annual loss rates of siltation in most
reservoirs are 145 percent to 875 percent of the figures assumed at the
time of construction."(3)
The Canadian Yangtze Joint Venture (CYJV) estimates that the equilibrium
would be reached when the 90 to 95 percent of the sediment entering is
flushed through the reservoir (4). This would be in about 100 years (CYJV,
pp. 1-4). A forecast of an approximate condition 100 years ahead is hardly
a fiscal surety.
A most important problem involves the actual management of the facility.
Between May 1 and September 30, sediment-laden large flows of water will
be discharged in order to carry away its sediment. But those same large
flows of water cannot be used to fill the reservoir to provide for the
winter needs. Moreover, the large flows that carry the sediment can also
be the cause of floods. Because the high sediment inflow corresponds
closely with the high water inflow, the needs of flood storage and
sediment removal are antithetical.
In the case of a possible flood condition upstream of Three Gorges, the
prudent course of action would be to close or partially close the
discharge gates so that potentially destructive floods would be prevented
by storage of the incoming water. But the incoming high flood flow also
carries the most sediment and could not be flushed through the reservoir.
The sediment so held as a deposit in the reservoir settles on the bed, and
requires more force to dislodge it than was necessary to keep it flowing
to the outlet gates.
Year to year, this simultaneous need to pass sediment through the
reservoir and the need to store water for power or flood control requires
a neat and sophisticated day-to-day forecast of inflow of water and
sediment. The hope is that a slight lack of simultaneity of water and
sediment inflows could be used to move sediment just ahead of or behind
the greatest flow of water. Experience in dam operation in the
United States
shows that such delicate management is uncommon. The delicacy of such an
operation is emphasized by the fact that the sediment rating curves do not
show the common lack of coincidence of maximum water flow and maximum
sediment flow. Usually the sediment is greatest in the early or rising
limb of the annual hydrograph, but at Three Gorges, the rating curves are
not looped (vol. 5, pp. 5-16, 5-18, 5-19). Therefore, dependence on a lack
of coincidence is a poor procedure on which simultaneous flood control and
sediment flushing must rest.
Another aspect of possible trouble is in the forecast, 90 to 100 years in
the future, of the final slope of the deposited sediment in the reservoir.
If the slope is greater than forecast, the deposition in the channel at
the head of the reservoir would be much steeper than forecast, leading to
unanticipated flooding. The analyses of this important matter were done by
computation and models, with no detailed analyses of experience in other
reservoirs of the world. Only one page in the CYJV report was devoted to
another example - that of Sanmenxia Reservoir in
China
- but no statement was made concerning the depositional slope. The one
example is hardly reassuring because after two years of operation,
1960-62, the sediment deposition was so large that the operation of the
reservoir was completely altered. "New tunnels were driven...and some
penstocks were converted to spillways" (CYJV, vol. 5, pp. 7-20). The
rate of deposition had been grossly underestimated and remedial action was
needed after only two years.
Another possible problem is in the assumptions regarding bedload, the
coarse material that will eventually accumulate at the head of the
reservoir. The gravel component in the sediment was deemed so small that
it was "not considered in reservoir sedimentation calculations"
(CYJV vol. 5, pp. 1-2). The gravel's portion is of great importance at the
head of the reservoir. The report suggests that "gravel bedload
amounting to perhaps 200,000 m3 per year may need to be dredged for the
Chongquing reach" for the chosen elevation of the FCL.
The bulk of the sediment that will be deposited in the reservoir will be
the sand portion. The gravel- and cobble-size material will be the first
to drop out of the flow and will accumulate near the head of the
reservoir. The slope of this coarse deposit will determine how far
upstream it will extend and thus the extent to which it will result in
flooding nearby Chongquing and harm the navigation channel and facilities.
The project plan apparently expects that as the final condition is reached
in 100 years, all the incoming gravel will have to be dredged, each year,
into the indefinite future. If the incoming load is underestimated, these
costs could be so financially burdensome that the original benefit-cost
relationship is quite discredited.
The effect of sediment storage in the reservoir on the channels downstream
is given little importance. The report implies that until equilibrium is
established, about 100 years hence, water with little sediment will be
discharged and "there will be degradation below Gezhouba and the
alluvial reaches of the middle and lower Yangtze" (CYJV vol. 5 pp.
1-10). But the report says "some degradation may be beneficial."
Experience in the
United States
of degradation by clear water below a dam hardly justifies such optimism.
Below Hoover Dam on the
Colorado River
, the degradation was some 35 feet. Below
Fort
Peck
on the
Missouri
, there was serious bank erosion. Discharge of water with a low sediment
content for 100 years is not likely to be insignificant in its effect on
downstream channels. If degradation is great, diversion works could be
destroyed. If bank erosion is serious, the extensive levees may be in
jeopardy - levees critical to the flood management system of the river's
lower reaches.
Downstream of Three Gorges, the alluvial plain is settled by several
millions of people who all depend on diversion works for irrigation water
and on massive levies to confine floodwaters. The morphology and stability
of the channels on this alluvial plain are conditioned by the combination
of water and sediment that has characterized the river for hundreds of
years. If clear water from Three Gorges flows into such a channel part of
each year for many decades, the channel will react.(5) Experience in many
countries demonstrates that the reaction will be some combination of bed
erosion and bank erosion.
Downcutting could leave diversion works and canals high above the river
level and thus require new engineering facilities to correct the problem.
Bank erosion would tend to undermine the flood control levees and thus
demand levee rehabilitation.
The analysis of the CYJV says that the effect of sediment on the discharge
tubes in the dam would be minimal. It speaks only of abrasion to the
penstocks and turbines. But the experience in the United States is that
the discharge of large volumes of water through tunnels, pipes and
penstocks results in serious cavitation, due to local below-atmospheric
pressure resulting in pieces of rock and concrete blown off the walls of
the tunnels, especially at the entrance. This created a maintenance
problem as well as decision to refrain from extended discharge at high
rates for long periods. This potential problem deserves more attention
than has been given in the analyses at Three Gorges.
Works Cited
(1) Hu Chunhong, 1995, Controlling Reservoir Sedimentation in China,
Hydropower and Dams, March issue, pp. 50-52.
(2) Morris, G.L. and Rao P.R., 1991, Workshop on Management of Reservoir
Sedimentation.
(3) Murty, K.S., 1989, Soil Erosion in India, River Sedimentation,
vol. 1, Intl. Res. & Train Center on Erosion, Beijing.
(4) Canadian Yangtze Joint Venture, 1988, Three Gorges Water Control
Project Feasibility Study, vol. 5, Sediment.
(5) China Yangtze Three Gorges Development Corporation, Environmental
Impact Statement for the Yangtze Three Gorges Project, a brief edition:
Science Press, Beijing.
This article was found
at: http://irn.org/programs/threeg/leopold.html
|